Presentation made on a " 6 Storied Residential Building" for Quantity Surveying , CE-208 .

PRESENTATION OF QUANTITY SURVEYING CE-208 Compiled by – Group-01, 2nd Year, 2nd Semester, Section-C, Department of Civil Engineering, Ahsanullah University of Science & Technology

CONTRIBUTED BY Arafat Chowdhury (GL) (12-01-03-116)  Sagar Ahmed (12-01-03-102)  Farah Tabassum Nova (12-01-03-103)  Abdul Aahad (12-01-03-104)  S.M. Rafsan (12-01-03-105)  Saffat Rabby Munayem (12-01-03-106)  Abdullah Al Hasan (12-01-03-107)  Shams Mashrur Khan (12-01-03-109)  Monisha Podder Puja (12-01-03-110)  Md. Mamun Or Rashid (12-01-03-111)          Mohibul Hasan Abir (12-01-03-112) Md. Amzad Hossain Patowary (12-01-03-114) Khurrom Jah Murad (12-01-03-115) Asif Mahmud Tanveer (12-01-03-117) Bishwojith Deb (12-01-03-120) Shuvo Ghosh (12-01-03-121) Fatema Rahman Jisha (12-01-03-122) Sabrina Zissan Rafa (12-01-03-124) Md.Asif Faisal Chowdhury (12-01-03-125)

Topic: Estimation of a Residential Building

CONTENTS:  Site Details  Typical Plan  Earthwork Excavation  Footing  Short Column  Grade Beam  Water Reservoir  Floor Slab  Beam & Column        Stairs Masonry Wall Others Plastering & Paint Ground Floor Over Head Tank Costing Estimation

Site Details Client: Mr. & Mrs. X Chowdhury. Contractor: Building Technology & Ideas (bti). Architecture: Mr. Tofayel Muhammad Sarwar. Engineer: MD. Shakhawat Hossain. Location: Plot No: 44, Firmgate, Dhaka. Description of Building: • (G+5) Storied. • units at each floor. • sft Building Name: bti Garden. Starting Time: January 2012 Ending Time: December 2014

Typical Plan

EARTHWORK EXCAVATION Excavation for Footing: 872.25cft Excavation for Underground Water Reservoir: 701cft Total Volume: 1574cft

ESTIMATION OF FOOTING Total Cement Concrete (CC) for (F1,F2,F3,F4) : 280+262+113+81= cft Total BFS for (F1,F2,F3,F4) : +196+84.5+72=545sft

SHORT COLUMN Total Cement Concrete (CC) for C ,C2,C3,C4 +35+34+39=131cft

REINFORCEMENT IN COLUMN Total Reinforcement for columns (C1,C2,C3,C4): Φ : 588 KG Φ : 74 KG Φ : 234 KG Grade Beam (GB) to PL: Φ : 75 KG Φ : 16 KG Φ : 22 KG

CC OF GRADE BEAM Length: 202ft Outflush: .5+0.5+0.75+1+1+0.75+0.5+0. +0.625+0.625+0.625+0.625+0. +0.5= 9ft Total Length: 202+9=211ft Cross Sectional Area: .25*1=1.25sft Volume of CC: 211*1.25=264cft

REINFORCEMENT OF GB (2-Top+1 Bottom)=633ft -Φ -Φ (2 Bottom)= 420ft -Φ (Extra Top)=291ft Total Length & Weight : Φ =420+291=711ft= 535KG Φ =633ft=305 KG Stirrup (For Mid Section): 1080ft Stirrup (For Support Section): 864ft Total Length & Weight : Φ ft= 370 KG =

UNDERGROUND WATER RESERVOIR CC Layer under UGWR (3 inches thick) : 53cft Bottom Slab (9 inches thick) : 158cft Wall (7 inches thick) : 226cft Top Slab (6 inches thick) : 78cft Total Volume: 515cft For Economical Purpose: BFS Around UGWR Wall (5 inches thick):186 cft Reinforcement Φ Bottom Slab+Wall+Top Slab: +4113+1420=6475ft=1220 KG

FLOOR SLAB CC & REINFORCEMENT BFS: 1454sft CC (3 inches Thickness) : .5cft Φ Φ = 9754ft=1936 KG = 375ft=102 KG

BEAMS Long Sec-B-1: Φ =28 KG Φ =113 KG Φ =37 KG Long Sec-B-2: Φ KG Φ KG Φ =21 KG Long Sec-B-3: Φ KG Φ KG Φ KG

Long Sec-B-4: Φ =84 KG Φ =124 KG Φ =37 KG Long Sec-B-7: Φ KG Φ KG Φ =73 KG Long Sec-B-5: Φ =88 KG Φ =146 KG Φ =37 KG Long Sec-B-8: Φ KG Φ =13 KG Long Sec-B-6: Φ =57 KG Φ =131 KG Φ =39 KG Long Sec-B-9: Φ KG Φ KG Φ KG Long Sec-B-10: Φ KG Φ KG Φ =31 KG Total Weight : Φ KG Φ KG Φ KG

Columns: CC: Volume: 171.875*5=860cft Reinforcement: Total Weight: Φ20=52*3=156KG Φ16=33.2*3= 100 KG For C4 : For C1+C2+C3: 1st Floor+ Ground : Volume: 1.5*1*10=15cft 1st Floor+ Ground : Volume: 1.25*1*10*3=37.5cft 2nd to 5th Floor: Volume: 1.5*1*9.5=14.25cft 2nd to 5th Floor: Volume: 1.25*1*9.5*3=35.625cft Total Weight: Φ20=52KG Φ16=33.2KG

STAIRS Flight: Steps: 9*12= 108 Steps (Each Floor: 2*9=18 Steps) Area: 0.5(1+0.5)*0.563=0.437 sft Volume of Flight cft Landing: Landings=13 Volume of Landings: *0.5*7.583*13= 200 cft

REINFORCEMENT OF STAIRS Landing: Φ : 1882ft Φ : 3250ft Flight: Φ ft Φ ft Total Length & Weight: Φ Φ : 2542ft=480 KG : 4460ft= 1210 KG Railing: Area: 130*3=390sft

Masonry Wall: Brick Required for 1st Floor: Length of Wall: 288.5ft Area of Wall: 2885sft Deduction for Windows & Door: 263+464.5=727.5sft Total Brick: 2157.5sft Brick Required for 2nd Floor: Length of Wall: 288.5ft Area of Wall: 2740.75sft Deduction for Windows & Door: 263+464.5=727.5sft Total Brick: 2013.5sft Brick Required for 3rd, 4th & 5th Floor: Length of Wall: 278ft Area of Wall: 2641sft Deduction for Windows & Door: 263+464.5=727.5sft Total Area of Brick: 1914sft

Others Tiles Window Grill: 1st & 2nd Floor: Left Side: 436.033sft Right Side: 410.649sft 1st & 2nd Floor: Area: 225sft 3rd & 5th Floor: Left Side: 405sft Right Side: 410.649sft th Floor: Left Side: 417.351sft Right Side: 410.649sft 3rd, 4th & 5th Floor: Area: 240sft

Reinforcement in Verandah Railing: Reinforcement in Cantilever: For 1st Floor & 2nd Floor (Φ10) : V1+V2+V6+V4= 43+42+36+19= 140sft 1st Floor (Φ20): 24+27=51 KG 2nd Floor (Φ20): 26+34=60 KG 3rd Floor (Φ20): 54+40=94 KG 4th Floor (Φ20): 53+31= 84 KG For 3rd Floor & 5th Floor (Φ10) : V1+V2+V5+V3= 43+42+27+36= 150sft GB Lap: For 4th Floor (Φ10) : V1+V2+V7+V3= 43+42+37+36= 160sft Φ16= 70ft= 34 KG Φ20= 67ft= 50 KG Reinforcement in Lintel: Length for 1st, 2nd ,3rd ,4th, 5th Floor (Φ20): 511ft Stirrup (Φ20) : 427.5ft Total Length (Φ20): 511+427.5= 940ft= 177 KG

Door Frame & Shutter: Window: 1st & 2nd Floor: Thai-Aluminium: Length: 22*0.25=5.5sft Glass: 30sft D1 (2 Pieces)= 3.333ft D2 (4 Pieces) = 3ft D3 (6 Pieces) = 2.5ft 3rd, 4th & 5th Floor: D1 (2 Pieces)= 3.333ft D2 (4 Pieces) = 3ft D3 (5 Pieces) = 2.5ft

Sanitary Pit: Height= 2.5 ft Length= 2ft Width= 2ft Brick Wall Perimeter: 2*(2.416+2.417)=9.667 Area: 9.667*2.5=25sft*10=250sft Cover: Volume of CC=20cft Weight of Φ 0 Reinforcement= KG

False Slab: Volume of CC: 9*24=216cft Length of Reinforcement (Φ ): 72+32=104*24=2496ft Lintel: Volume of CC: .458*80=117cft Length of Reinforcement (Φ *80=2240ft Kitchen Worktop: Volume of CC: .625*10=26.25cft Length of Reinforcement (Φ *10=420ft

Plastering: For 1st Floor: Length of Wall: 288.5ft Area of Wall: 2885sft Deduction for Windows & Door: 263+464.5=727.5sft Total Area of Inside: 2157.5sft Volume: 1078.5cft (0.5 inch Thickness) Total Area of Outside: 2157.5sft Volume: 1618.125cft inch Thickness) For 2nd Floor: Total Area of Outside: 2 .5sft Length of Wall: 288.5ft Volume: 1510.1255cft (0.75 inch Thickness) Area of Wall: 2740.75sft Deduction for Windows & Door: 263+464.5=727.5sft Total Area of Inside: .5sft Volume: .75cft (0.5 inch Thickness)

For 3rd, 4th & 5th Floor: Length of Wall: 278ft Area of Wall: 2641sft Deduction for Windows & Door: 263+464.5=727.5sft Total Area of Inside: 1914sft Volume: 957cft Total Area of Outside: 1914sft Volume: .5cft Paint: (Same as Plastering) Total Volume of Paint for inside: 1078.5+2013.5+957= 4050cft Total Volume of Paint for Outside: 1618.125+1510.1255+1435.5= 4564cft

Ground Floor: Boundary: Masonry Wall: 119.3*5*.4167= cft No. Of Bricks= 3443 Nos. Volume of Brick with Mortar: 300cft Volume of Brick without Mortar: 235cft Volume of Mortar: 65cft Volume of wetted Mortar: 65*1.5= .5cft Volume of Sand: 78cft Volume of Cement: 19.5cft=16 Bags Garage: Masonry Wall: .3*7*.4167=348cft No. Of Bricks= Nos. Volume of Brick with Mortar: cft Volume of Brick without Mortar: cft Volume of Mortar: cft Volume of wetted Mortar: cft Volume of Sand: cft Volume of Cement: cft=22 Bags Grill: No of Long Bar: 12 No of Short Bar: 480 Total Length of Φ Bar: 2868ft

Over Head Tank : Section B-1: Volume of CC: 87.5cft Reinforcement: 2-16 Length : 19ft+16ft=35ft mm= 25.25*2=50.5ft mm=42*2=84ft Section B-2: Volume of CC: 87.5cft Reinforcement: -16 Length +12=49ft mm= .25*2=54.5ft -16mm=27.25*2=54.5ft

ESTIMATION OF COST Labor Cost: (6 Labors, 1800 BDT/Day) ,42,000 BDT # Cement (2856 Bags*500 BDT) =14,28,000 BDT # Sand: cft (10,000BDT/1000cft)= 1,24,560 BDT # Brick: ,000 Nos ( 10 BDT/ Each)= 2,00,000 BDT Reinforcement: KG= 13,57,432 BDT Tiles: (2490sft*60 BDT/sft)= 1,49,420 BDT Thai- Aluminium & Glass: (5000*80)=4,00,000 BDT # Door : *10,000 =4,00,000 BDT Total Cost of Materials & Man Power: ,01,412 BDT Other Cost: # Plumbing System Cost: of Total Cost= 5,39,155 BDT # Electrical Cost: of Total Cost= 5,39,155 BDT # Elevator: Lac #Generator Lac Total Cost: ,79,722.00 BDT

FINALLY !

COPYRIGHT  This presentation is copyright protected by Arafat Chowdhury, Department of Civil Engineering, Ahsanullah University of Science & Technology (AUST) Dhaka, Bangladesh  If you want to present or use these slides for any purposes kindly contact to Arafat Chowdhury Thank you for watching & your precious time !

Add a comment

Related presentations

Related pages

4 Quantity Surveying - Documents

QUANTITY SURVEYING QUANTITY SURVEYING Materials Take Off Preparation and Measuring of Quantities: ... Quantity Surveying Presentation by 2-2_Sec-C,AUST.
Read more

Quantity Surveying Presentation - YouTube

Quantity Surveying Presentation Hor Weng Lim. Subscribe Subscribed Unsubscribe 1 1. Loading... Loading... ... Quantity Surveying course, ...
Read more

Quantity Surveying by P.T.joglekar - Documents

Share Quantity Surveying by P.T.joglekar. ... Traditional & Modern Quantity Surveying Practice ... Quantity Surveying Presentation by 2-2_Sec-C,AUST.
Read more

Popular Videos - Surveying & Quantity surveyor - YouTube

Popular Videos - Surveying & Quantity surveyor Surveying - Topic; 199 videos; 9,442 views; ... Quantity Surveying Presentation by Hor Weng Lim ...
Read more

Quantity surveyor - Wikipedia, the free encyclopedia

A quantity surveyor (QS) ... Traditional quantity surveying services. Cost planning; ... Notable Quantity Surveyors
Read more

BCIS Presentations - RICS

Presentations and papers presented by BCIS at conferences and ... RICS National Quantity Surveying and Construction Conference ... Find a surveying firm
Read more

An e-learning approach to quantity surveying measurement

Quantity surveying measurement adopts prescriptive processes which are underpinned by an ... concise and focussed presentation we have adopted, ...
Read more

Upcoming Events

History of Quantity Surveying; Annual Reports; Articles of Association; Code of Conduct; ... AIQS congratulates the Victorian Government. Posted on 6/05/2016
Read more