Program Overview

50 %
50 %
Information about Program Overview
Entertainment

Published on January 1, 2008

Author: Ethan

Source: authorstream.com

Slide1:  Presented by Program Overview Mr. Gary Davis Project Manager Ms. Vandi Leheny Project Manager Slide2:  Program Goals Authorities/Jurisdiction Wetlands Criteria Types of Permits Permit Timelines/Procedures Enforcement Agenda Slide3:  The following slides are Regulatory 101 and are intended to assist us in an effort to better communicate the Corps’ Regulatory Mission. Why we do what we do… Slide4:  Protect aquatic environment, including wetlands Enhance program administration efficiency Provide fair flexible and balanced decisions while allowing reasonable development Program Goals Slide5:  Rivers and Harbors Act Clean Water Act Regulatory Jurisdiction Slide6:  Authorities Slide7:  A PERMIT IS REQUIRED FOR THE CONSTRUCTION OF DAMS OR DIKES ACROSS ANY “NAVIGABLE WATERS OF THE U.S.” Section 9, Rivers and Harbors Act (RHA) of 1899 (33 USC 401) Slide8:  Prohibits the unauthorized obstruction or alteration of any navigable water of the U.S. Section 10 of the RHA of 1899 (33 USC 403) Slide9:  Structure(s) in over or under a navigable waterbody: Dredging or disposal of dredged material, excavation, or filling Any other obstacle or obstruction, or modification to navigable waters. What requires a Section 10 Permit? Slide10:  Section 404 of the Clean Water Act (33 USC 1344) Prohibits the discharge of dredged or fill material into all “waters of the United States, including wetlands” without obtaining a permit from the Corps of Engineers Slide11:  EPA, in conjunction with Army (Corps) will develop guidelines to be applied at each discharge site. These regulations are at 40 CFR 230, and are commonly called the Section 404(b)(1) Guidelines. EPA Administrator authorized to restrict or deny the use of any discharge site – “EPA’s veto authority.” Can be exercised before or after Corps reaches decision to issue a permit. (40 CFR 231) EPA has used very sparingly – approx. 10 times in 25 years Clean Water Act – Section 404(b)(1) Slide12:  Placement of fill material Slab-on-grade foundations Most road construction Dam construction and Impoundment Levee and dike construction Mechanized land clearing* Grading and landscaping* Certain pile-supported structures What requires a Section 404 Permit? Slide13:  Compliance with other laws (NEPA, ESA, NHPA, etc.) Other Authorities Slide14:  Rivers and Harbors Act Clean Water Act Regulatory Jurisdiction Slide15:  All waters currently used, used in the past, or susceptible to use in interstate or foreign commerce, including all tidal waters (e.g., navigable “in fact” or by definition). Interstate waters including interstate wetlands. Intrastate waters whose use or degradation could affect interstate or foreign commerce All impoundments of waters defined as waters of the U.S. Tributaries of the above. The territorial seas. Wetlands adjacent to the above waters. - Jurisdiction - Waters of the U.S. (33 CRF 328) Slide16:  EPA Regulations applied by the Corps Corps policy is that they are the substantive environmental criteria against which all proposed discharges of dredged or fill material into waters of the United States must be measured against. Guidelines for Specification of Disposal Sites for Dredged or Fill Material (40 CFR 230) [Commonly known as the Section 404(b)(1) Guidelines] Slide17:  No discharge shall be permitted if there is a practicablealternative. Must be the least environmentally damaging practicable alternative. Practicable defined as available and capable of being done after taking into consideration costs, logistics, and existing technology in light of the overall project purpose. Rebuttable presumptions for non-water dependent discharges to special aquatic sites: Alternatives are presumed to be available Alternatives presumed to be less damaging Applicant must clearly and convincingly rebut presumptions Restrictions on Discharge (230.10) Slide18:  No disharge permitted if: Violates any State water quality standard or toxic effluent standards Jeopardizes existence of endangered species or destroys or adversely modifies designated critical habitat Results in significant degradation All appropriate and practicable steps to minimize adverse effects are not taken Corps determines that it does not comply with Guidelines Restrictions on Discharge (230.10) continued Slide19:  What are wetlands? Slide20:  Those areas inundated or saturated by surface or ground water at a frequency and duration to support, and that under normal circumstances do support, a prevalence of vegetation adapted for life in saturated soil conditions. Wetlands generally include marshes, swamps, bogs, and similar areas; also includes special aquatic sites such as riffle and pool complexes and submerged vegetation. Wetland Definition [33 CRF 328(3)(B)] Slide21:  Hydrology Hydrophytic Vegetation Hydric Soils Wetlands are identified and delineated using the Corps 1987 Wetland Delineation Manual. Wetland Criteria [33 CRF 328(3)(B)] Slide22:  Water Quality Improvement Water Supply Flood Protection Recreation and aesthetics Why are wetlands important? Slide23:  2005 Gallup survey says that 93% of Americans believe the Clean Water Act plays an important role in maintaining safe/clean water for the future. 1 acre of wetlands can filter over 30,000 gallons of water per hour. Value, Yes or No? Slide24:  Water Quality Improvement Water Supply Flood Protection Recreation and aesthetics Why are wetlands important? Slide25:  How Do We Regulate Work? Permits Enforcement Slide26:  Types of Permits General Permits Include: Regional Programmatic Nationwide Standard Permits Include: Letter of Permission Individual Provisional Emergency After the Fact Slide27:  Types of GP’s: Regional Programmatic Nationwide Permit that most minor activities are authorized under. Currently AL Power is administering our GP Program on AL Power Lakes. GP for Lakes/Resource Offices forthcoming. General Permits (GP’s) Slide28:  May authorize minor filling, roads, utility lines, maintenance of existing structures and other minor activities. Most NWPs for fill require mitigation; greater than a 1/10th of an acre. Nationwide Permits (NWP) (33CFR 330.1) Standard Permit (SP):  Standard Permit (SP) Types of SP’s: Letter of Permission Individual Provisional Emergency After the Fact Permit that most activities that may cause more than minimal adverse effect to the aquatic environment Exceed terms and conditions of GP Slide30:  Typically used to authorize activities that may not fit the General Permit, but still have relatively minor impacts to waters and no impacts to wetlands; no appreciable opposition. small marinas long bulkheads minor dredging Requires agency review by pretty much every state and federal resource agency. Separate authorization from AL Power, USACE and the State required. Letters of Permission Slide31:  This is where the leftovers go. Anything that does not fit a NWP, GP or qualify for an LOP has to go through this process. Requires Public Notice and review by pretty much every state and federal resource agency. Long, complicated and detailed process. Most require mitigation. Individual Permit Slide32:  Approximate Timelines Regional – 30-45 days Programmatic – 45 days Nationwide – 45 days Letter of Permission – 30 days Provisional – 45 days Emergency - 24-72 hours After the Fact NWP within approximately 45 days IP 3-6 months Individual – 3-6 months Slide33:  Procedures Pre-application consultation (optional, but highly encouraged) Complete Application submitted File number assigned (ORM) and PM assigned. Acknowledgement letter sent to applicant File reviewed for completeness within 10 days of receipt and determination of applicable permit/JD procedure. Request for additional information if necessary Public notice issued (within 15 days of completed application); 15-30 day comment period Public notice is reviewed by Corps and “public, groups, agencies” Corps considers all comments & consults with other agencies if appropriate Applicant could be asked to provide additional information Public hearing held, if requested (can be denied) Slide34:  Procedures Complete Public Interest Review: Evaluation Factors Considered: Conservation-Economics-Aesthetics-Wetlands-Historic properties-Flood Hazards-Floodplain Values-Land Use-Navigation-Recreation-Energy Needs-Mineral Needs-Safety-Water Quality-Fish & wildlife values-Shore erosion & accretion-Water supply & conservation-Food & Fiber Production-Considerations of Property Ownership-General Environmental Concerns-Needs & Welfare of the People Legal Requirements: Water Quality Certification (404 actions) Coastal Zone Consistency (Tidewater counties) 404(b)(1) Compliance (404 actions) NEPA Compliance (EA, FONSI, EIS) COE makes decision and writes decision document Permit issued or denied (applicant advised of reason) Administrative appeal process (optional) Slide35:  Work without a DA permit Work outside conditions of DA permit Amounts: Criminal: various fine amount per day and/or imprisonment Civil: up to $25,000 per day Class I Administrative: up to $25,000 Class II Administrative: up to $125,000 EPA Referral Enforcement Actions Is it wet? :  Is it wet? Don’t hesitate to ask… before you do the work! Slide37:  Questions Thank you for your interest in the U.S. Army Corps of Engineers Regulatory Program

Add a comment

Related presentations

Related pages

Program Overview - FFS Online

Program Overview. The FFS Online program takes you through modules that you access through this protected Web site. These modules include valuable ...
Read more

Program Overview | The Prudential Spirit Of Community Awards

The Prudential Spirit of Community Awards program is the United States' largest youth recognition program based exclusively on volunteer community service.
Read more

IMPRS-CS: Program Overview

Program Overview. The International Max Planck Research School for Computer Science (IMPRS-CS) offers a fully funded graduate program in cooperation with ...
Read more

ZEF Program Overview

ZEF’s doctoral program is international and diverse. Nearly 600 students have joined our program since its start in 1999, representing nearly 90 countries.
Read more

Program Overview - Academy of Management

The 77th Annual Meeting of the Academy of Management - August 4-8, 2017 - Atlanta, Georgia, USA
Read more

FMX: Program 2016

Program. Program 2016; Recorded Presentations from FMX 2016; The FMX Program is online! ... Program Overview. Overview Schedule Speakers Back. Loading ...
Read more

TED2016 | Program | Program overview - Conferences

The TED2016 experience will include: A fast-paced, highly curated five-day stage program featuring TED's famous 18-minute talks, plus music, comedy, tech ...
Read more

Program Overview | FedRAMP

Program Overview. Cloud solutions allow for faster processing and more elasticity in computing in an on demand, more efficient platform. However ...
Read more

Program overview - Reeve Foundation

Program overview As a pillar of the Paralysis Resource Center, the Quality of Life Grants Program awards financial support to nonprofit ...
Read more

PROGRAM OVERVIEW - Power & Care

Power & Care is a Mind and Life Dialogue of leading experts with His Holiness the Dalai Lama, from September 9-11, 2016, in Brussels, Belgium.
Read more