1. 1

2. RUBNAWAZ 2015-UET-CCET-CIVIL-02 3rd SEMESTER CIVIL ENGINEERING DEPARTMENT

3. February 2012 GOVERNMENT OF THE PUNJAB COMMUNICATION & WORKS DEPARTMENT Construction of Flyover on G.T Road at Aziz Cross Gujranwala

4. February 2012 GOVERNMENT OF THE PUNJAB CONSTRUCTION OF FLYOVER ON G.T ROAD AT AZIZ CROSS GUJRANWALA Construction of Flyover on G.T Road at Aziz Cross Gujranwala

5. SALIENT FEATURE  ADP (2016-17) Gr. Sr. No. 2775  Approved Cost Rs. 6672 Million  Construction Cost Rs. 3435 M  Land Acquisition (80 Kanal) Rs. 2920 M  Miscellaneous Rs. 317 M  Consultant M/s NESPAK  Contract M/s NLC  Client C & W Dept  Agreement Amount Rs.3115 M (9.35% below Est.cost)  Date of Commencement 30.01.2016  Date of Completion 29.11.2016

6. INTRODUCTION  Aziz Cross project is a signal free interchange with partial clover leaf system and two additional directional ramps. Clover leaf interchange Partial Clover leaf interchange with two directional ramps instead of loops

7. INTRODUCTION  There are normally 32 conflicts at any interchange which are completely resolved at Aziz Cross. 32 No. Traffic Conflicts Traffic Count 2014

8. 31,775 36,543 17,541 RAWALPINDI LAHORE GUJRANWALA SIALKOT 13,000 NEW TRAFFIC DIRECTIONS & VOLUMES (ADT 2014)

9. BASIC COMPONENTS OF FLYOVER Bridge cross-section can be divided into two portions. 1. Super Structure This portion receives the live load directly. For example, Box Girder 2. Sub Structure This Portion supports the entire structure and live loads.  Piles  Pile cap  Piers  Abutments Web Web Pier Canopy Pier Shaft Pile Cap Pile Pile Pile Super Structure Sub Structure

10. CONCRETE PILES A pile is a vertical structural element of a deep foundation which transfers super structure loads to the earth farther down from the surface to a subsurface layer.

11. PILE CAP PILE CAP Pile cap is a thick reinforced concrete mat that rests on concrete piles that have been casted into ground. concrete pile cap distributes the load of the superstructure (from piers and abutments into the piles. Pile Cap Piles Pier

12. PILE CAP AND PIER PIER A pier is a reinforced, raised structure in form of pillars typically supported by well-spaced pile caps. It transfers the loads from deck to pile caps. For this project, special shape of pier is adopted. It as two components 1. Pier Shaft as column 2. Pier Canopy as transom Pier Canopy Pier Shaft Box Girder

13. Abutment refers to the substructure at the ends of a bridge span. It supports;  Super Structure load  Live Load  Lateral Earth Pressure ABUTMENTS Abutment Pile Cap Piles

14. REINFORCED EARTH WORK  Reinforced earth wall is earth retaining structure and provided at approaches (from road level to bridge level).  The key components of a Reinforced Earth wall are geo-strips, granular backfill and precast concrete facing panels.  The frictional bond between the backfill supports the lateral earth pressure and stresses induced due to traffic load.

15. ABUTMENT 01 ABUTMENT 06 LOOP 2 ABUTMENT 07

16. REINFORCED EARTH WORK

17. PRE-STRESSED BOX GIRDERS Bottom View of Box Girder Piers  An optimal and most efficient design of beam is box girder. A box girder consists of enclosed tube with multiple walls.  The advantage of a box girder is that it better resists torsion. Having multiple vertical webs, it can also carry more load than an I-shape girder of equal height. Pre-stressing Mechanism

18. SCOPE OF WORK 12/14/2016 Flyover 1 Length 301.5 Piles 80 P. Cap 15 Piers 15 Abt. 2 Spans 10Flyover 2 Length 301.5 Piles 66 P. Cap 11 Piers 12 Abt. 2 Spans 10 Flyover 5 Length 80.05 Piles 38 P. Cap 4 Piers 6 Abt. 2 Spans 3Flyover 3 Length 417.3 Piles 64 P. Cap 15 Piers 13 Abt. 2 Spans 14 Flyover 4 Length 564.41 Piles 84 P. Cap 20 Piers 18 Abt. 2 Spans 18 RWP LHR GRW SKT Pile= 332 Ramp 3 (L=361.14m) Ramp 6(L=369.39 m) Bridge approaches (841m) Pile caps=65 Ramp 3A(L=573.11m) Ramp 7(L=369.39 m) Abutment= 10 Ramp 4( L=379.35m) Loop 1(270.18m) Bridge Lengths(1664m) Piers=60 Ramp 5 (L=846.94m) Loop 2(L=195.23) Road Length (4660m)

19. FLYOVER S– 1, 2, 3 & 4  Piles 100 % Completed (294 out of 294)  Pile Caps 100 % Completed (62 out of 62)  Piers 100 % Completed (62 out of 62)  Abutment 100 % Completed (8 out of 8)  Box Girders 20% in progress (4 out of 17)  Reinforce Earth Wall 50 % Completed (0.6 km out of 1.12 km)  At Grade Roads 60% up to WBM (3 Km out of 5 Km) RAILWAY BRIDGE  Piles 100% Completed (38 out of 38)  Pile Caps 100% Completed (4 out of 4)  Piers 100% Completed (2 out of 2)  Transoms 50% Completed (1 out of 2)  Abutments 50% Completed (1 out of 2)  Pre-cast Girders 100% Completed (21 out of 21) PHYSICAL PROGRESS

20. Year Release Expr. %age Remarks 2014-15 2500 2500 100% Payment made for land acquisition. 2015-16 1555 1555 100% Rs. 400 M land acquisition. Rs. 215 M shifting of services. Rs. 940 M paid to NLC. 2016-17 1000 510 51% Rs. 510 M paid to NLC. FINANCIAL PROGRESS