Bill 50 Powerpoint Jan 7 2010

50 %
50 %
Information about Bill 50 Powerpoint Jan 7 2010
Business

Published on January 14, 2010

Author: ELCAlberta

Source: slideshare.net

Description

On January 7th 2010, Laura Bowman presented a lunch seminar on Bill 50, the Electric Statutes Amendment Act, 2009. This controversial bill was tabled in the summer and has been part of a storm of publicity and often confusing and contradictory information ever since.

Electricity planning and approval in Alberta Laura Bowman staff lawyer Environmental Law Centre January 7, 2010 Bill 50

Presentation Outline Report outline Presentation Outline: Major players How it works – Pre Bill 50 Problems with pre-Bill 50 What Bill 50 does and does not do Moving forward? Bill 50

Major players

How it works – Pre Bill 50

Problems with pre-Bill 50

What Bill 50 does and does not do

Moving forward?

Major Players Alberta Electricity System Operator (AESO) also known as ISO Alberta Utilities Commission (AUC) Major Players Bill 50 View slide

Alberta Electricity System Operator (AESO) also known as ISO

Alberta Utilities Commission (AUC)

How it works 1) Needs Identification AESO develops forecasts and plans for transmission Needs I.D. document (NID) for upgrades etc. AUC reviews the NID is it required? is it in the public interest? If yes, the NID is approved Affected parties can participate (narrow) AUC rules require AESO Consultations (broad) Consultation with Private companies only How it worked pre Bill 50 Bill 50 View slide

AUC reviews the NID

is it required?

is it in the public interest?

Private company applies for a permit to construct And operate from AUC AUC decides required or in the Public interest ? May vary the route, technical Issues, etc. Approves/denies/varies AESO directs a private Transmission company to Apply to fulfill the needs AESO reviews the application Affected parties can participate (narrow) 2) Permit Application How it worked pre Bill 50 Bill 50

AUC decides required or

in the Public interest ?

May vary the route, technical Issues, etc.

Approves/denies/varies

Big problems Pre-Bill 50 process presented problems: Identifying need AESO mandate Public doesn’t have right to participate No right to a hearing How it worked pre Bill 50 Bill 50

Identifying need

AESO mandate

Public doesn’t have right to participate

No right to a hearing

The much hated standing test and AUC process Directly and adversely affected people only (since 1960s) Must have a legally recognized interest or right (i.e. property rights), must be distinct from community as a whole. Not the public. AUC has required proof on balance of probabilities of declining property values, health risks, etc. Cannot cross-examine a company rebuttal. (for example, AUC decision 2008-128)

Directly and adversely affected people only (since 1960s) Must have a legally recognized interest or right (i.e. property rights), must be distinct from community as a whole. Not the public.

AUC has required proof on balance of probabilities of declining property values, health risks, etc. Cannot cross-examine a company rebuttal.

(for example, AUC decision 2008-128)

The Result Some people cannot participate at all . “ directly and adversely affected” people participate but become frustrated. The public interest is not well-served. The Result? How it worked pre Bill 50 Bill 50

Some people cannot participate at all .

“ directly and adversely affected” people participate but become frustrated.

The public interest is not well-served.

What is Bill 50? The Electric Statutes Amendment Act , 2009 passed Nov 25, 2009. Amends 3 statutes: Alberta Utilities Commission Act , Electric Utilities Act , and the Hydro and Electric Energy Act. Creates new category of “Critical Transmission Infrastructure” (CTI) Adds regulation-making powers and Cabinet power to designate CTI Designates critical transmission projects Bill 50

The Electric Statutes Amendment Act , 2009 passed Nov 25, 2009.

Amends 3 statutes: Alberta Utilities Commission Act , Electric Utilities Act , and the Hydro and Electric Energy Act.

Creates new category of “Critical Transmission Infrastructure” (CTI)

Adds regulation-making powers and Cabinet power to designate CTI

Designates critical transmission projects

Bill 50 New process AESO develops forecasts and plans for transmission Consultation with Private companies only Cabinet decides if Transmission in AESO Plan is “critical” And chooses Private company to Apply for permit Critical permit application to AUC But AUC has ?little? jurisdiction To refuse or vary Affected parties can participate (narrow ) Permit approved (whether or not required) If in the public interest* What Bill 50 Does Bill 50

What Bill 50 Does What projects can be designated “Critical”? Project must be contained in an AESO plan under the Transmission Regulation The project must also be: an intertie OR “ serve areas of renewable energy” (not defined) OR is a double circuit transmission facility that is designed to be energized at a nominal voltage at or greater than 240 kV, OR Bill 50

What projects can be designated “Critical”?

Project must be contained in an AESO plan under the Transmission Regulation

The project must also be:

an intertie OR

“ serve areas of renewable energy” (not defined) OR

is a double circuit transmission facility that is designed to be energized at a nominal voltage at or greater than 240 kV, OR

What Bill 50 Does … Or anything else! Is, in the opinion of the Lieutenant Governor in Council, critical* to ensure the safe, reliable and economic operation of the interconnected electric system. Critical is not defined, how determined? “ safe, reliable and economic” replaces all other considerations in the legislation. For example, public interest, cost. Bill 50

… Or anything else!

Is, in the opinion of the Lieutenant Governor in Council, critical* to ensure the safe, reliable and economic operation of the interconnected electric system.

Critical is not defined, how determined?

“ safe, reliable and economic” replaces all other considerations in the legislation. For example, public interest, cost.

What Bill 50 Does Bill 50 Amendments on Nov 24 Phased implementation of new lines: AESO to publish “milestones” cost reporting public interest put back into the permit hearing, so AUC has some jurisdiction

Phased implementation of new lines: AESO to publish “milestones”

cost reporting

public interest put back into the permit hearing, so AUC has some jurisdiction

Two 500 kV transmission facilities from the Edmonton area to Fort McMurray Two high voltage 500 kV direct current transmission facilities between the Edmonton and Calgary regions. Two 500 kV AC lines from the Wabamun Lake/Edmonton area to the Northwest region (not in Bill 50) Southern AB Transmission Loop (wind) Not in Bill 50 4 interties NSEW

Doesn’t fix limitations of need identification or planning AESO still prepares a transmission “plan” with discussion of generation forecasts (July 2009) Transmission lines are still exempt from approvals and EA process under the EPEA (since 2008) AUC still considers site issues, although powers are now more limited No change in process where transmission is not designated critical Does not change “standing” to appear before AUC. What Bill 50 Does Not Do Bill 50

Doesn’t fix limitations of need identification or planning

AESO still prepares a transmission “plan” with discussion of generation forecasts (July 2009)

Transmission lines are still exempt from approvals and EA process under the EPEA (since 2008)

AUC still considers site issues, although powers are now more limited

No change in process where transmission is not designated critical

Does not change “standing” to appear before AUC.

So, what does this mean for me? I have a transmission line concern, is there anything I can do with Bill 50?

I have a transmission line concern, is there anything I can do with Bill 50?

Understand the process! Bill 50 means that participation in forecasting and planning with the AESO is more important than ever. Engage with the AESO early on. Engage politically early on, only Cabinet decides if lines are critical, Director of ABENV decides if EA. Use other tools, like lobbyist registry. Just because a line is “critical” does not mean there is no more process, AUC permit application hearings are also important processes for critical transmission. Engagement after Bill 50

Bill 50 means that participation in forecasting and planning with the AESO is more important than ever. Engage with the AESO early on.

Engage politically early on, only Cabinet decides if lines are critical, Director of ABENV decides if EA. Use other tools, like lobbyist registry.

Just because a line is “critical” does not mean there is no more process, AUC permit application hearings are also important processes for critical transmission.

Engagement after Bill 50 New regulation powers in Bill 50: (v.1) respecting the planning, development, construction and operation of transmission facilities, including (A) critical transmission infrastructure, (B) interties, and (C) transmission facilities to serve areas of renewable energy, Be aware that this is coming, see what you can do to make these regulations as good as you can!

utilize renewable incentives in the Bill! Realize that it is not much worse than the pre-Bill 50 situation, you are likely to get cut out of the need process either way. Most people won’t notice much difference. Engagement after Bill 50 Is it all bad? …No, New regulation power for all renewable transmission, make the most of it. Possibility of “fast-tracking” renewable transmission projects with critical designations. Some cons = siting issues but pros include climate change benefit potential.

Realize that it is not much worse than the pre-Bill 50 situation, you are likely to get cut out of the need process either way. Most people won’t notice much difference.

New regulation power for all renewable transmission, make the most of it.

Possibility of “fast-tracking” renewable transmission projects with critical designations. Some cons = siting issues but pros include climate change benefit potential.

Engagement after Bill 50 Interties and exports National Energy Board (see Canada Gazette) New Bill 50 Regulations

Interties and exports

National Energy Board (see Canada Gazette)

New Bill 50 Regulations

Is there a better way to do this? Integrated transmission and generation planning with public participation would help First evaluate trends and study usage of electricity. When? Why? Then set renewable generation priorities, incentives and identify conservation opportunities. Examine all the available options! Make environment a priority. Then decide how to get any necessary new electricity to consumers with transmission.

Integrated transmission and generation planning with public participation would help

First evaluate trends and study usage of electricity. When? Why?

Then set renewable generation priorities, incentives and identify conservation opportunities.

Examine all the available options! Make environment a priority.

Then decide how to get any necessary new electricity to consumers with transmission.

Thank you Questions? Environmental Law Centre [email_address]

Add a comment

Related presentations

Boat chandlery

Boat chandlery

October 26, 2014

http://ecommerce-for-business.com/shackles-boats-theboatonlinestore/ We offer a ...

http://vendere-su-internet.com/shackles-for-boats-from-theboatonlinestore/ Moori...

Silver bar!

Silver bar!

October 21, 2014

Pretty similar to gold bars are these silver slabs. Silver is considered as the mo...

Gold coin prices!

Gold coin prices!

October 21, 2014

If you are an investor of gold bars and coins, one of the major things that you ou...

CyberSecurity's social media stats for one week as of Oct 21st 2014

CyberSecurity's social media stats for one week as of Oct 28th 2014

Related pages

So erstellen Sie eine Diashow mit Powerpoint - PC-WELT

Windows 7 Windows 8 ... 243, 50 € Versandk.: 3,00 ... Microsoft PowerPoint 2010 ESD DE Win.
Read more

Al Gore - Wikipedia, the free encyclopedia

Al Gore; 45th Vice President of ... The bill was passed on ... This 7–2 vote ruled that the standards the Florida Supreme Court provided for a ...
Read more

2010s - Wikipedia, the free encyclopedia

1980s 1990s 2000s – 2010s – 2020s 2030s 2040s: ... April 7, 2010 – Kyrgyz President ... the widely criticised Stop Online Piracy Act bill was ...
Read more

Office Vorlagen - Top 50 Pack - Download - CHIP

Office Vorlagen - Top 50 Pack Deutsch: ... Excel und PowerPoint. ... Office 2010 oder Office 2013.
Read more

Facts About Microsoft | News Center

Facts About Microsoft Image Gallery ... Dec. 7, 1995: Bill Gates outlines Microsoft’s commitment to ... Jan. 15, 2002: Bill Gates outlines Microsoft’s ...
Read more

Bill Gates – Wikipedia

William „Bill“ Henry Gates III, KBE ... mit einem geschätzten Vermögen von 72,7 Mrd. ... Januar 2010 gaben Bill und Melinda Gates bekannt, ...
Read more

The Official Website of the Buffalo Bills

Check out photos of the Buffalo Bills 2016 rookie class participating in minicamp. ... (7:53) Posted May 5, 2016. Go ... 50 Yard Finish: ...
Read more

Solutions Guide: Please do not present as your own

Title: Solutions Guide: Please do not present as your own Author: BusinessTutor Last modified by: BusinessTutor Created Date: 5/7/2010 5:30:00 AM
Read more

PowerPoint Presentation

Author: Ayako Created Date: 05/17/2010 05:07:23 Title: PowerPoint Presentation Last modified by: Bill & Inge Company: Grizli777
Read more

Bilanzrechtsmodernisierungsgesetz – Wikipedia

... wenn sie 500.000 Euro Umsatz und 50.000 Euro Gewinn an zwei aufeinander folgenden Geschäftsjahren ... Die Bilanzrechtsreform 2010/11. ... Jan (2009 ...
Read more